12750 CY of RCC produced and placed in 9″ lifts using paving equipment. The use of paving equipment allowed the dam to be constructed with a minimum use of formwork, which enhanced the construction schedule.
12750 CY of RCC produced and placed in 9″ lifts using paving equipment. The use of paving equipment allowed the dam to be constructed with a minimum use of formwork, which enhanced the construction schedule.