Brookley Field – Taxiway H


A.G. Peltz placed 18,178 SY of 16” PCC Pavement and 6” of Econocrete for a new taxiway project at Brookley Field in Mobile, AL. The project took 25 production days to complete with the first phase of the two-phase project completed in January of 2019. The PCC placement was completed with a Wirtgen 64 paver at 25’ lane widths with contraction joints sawn at 12.5’ intervals. The concrete was supplied by Bayou Concrete.

PROJECT: Taxiway H Brookley Field
OWNER: Mobile Airport Authority
DESIGNER(S): Michael Baker International, Bobby Odom
GENERAL CONTRACTOR: John G. Walton Construction
START DATE: Jan 2019
COMPLETION DATE: June 2019