Brookley Field – Taxiway H

A.G. Peltz placed 18,178 SY of 16” PCC Pavement and 6” of Econocrete for a new taxiway project at Brookley Field in Mobile, AL. The project took 25 production days to complete with the first phase of the two-phase project completed in January of 2019. The PCC placement was completed with a Wirtgen 64 paver at 25’ lane widths with contraction joints sawn at 12.5’ intervals. The concrete was supplied by Bayou Concrete.

  • PROJECT: Taxiway H Brookley Field
  • OWNER: Mobile Airport Authority
  • DESIGNER(S): Michael Baker International, Bobby Odom
  • GENERAL CONTRACTOR: John G. Walton Construction
  • START DATE: Jan 2019
  • COMPLETION DATE: June 2019